Cannon House Office Building Renewal Project’s Punch List and Warranty Work Process Lacked Sufficient Oversight
Report Information
Recommendations
We recommend the Cannon House Office Building Renewal Project team review all items listed as warranty items for Phase 2 and ensure they are (1) properly categorized as punchlist (also includes in-scope work), warranty or latent defect, (2) correctly...
We recommend for those items categorized as punchlist (in-scope work) and completed during and/or after the warranty period, the Cannon House Office Building Renewal Project team should negotiate an extended warranty period with the Construction Manager...
We recommend the Cannon House Office Building Renewal Project team improve its process for managing warranty items to ensure the only items included on its warranty list are those that meet the definition and description of a warranty item provided in...
We recommend the Cannon House Office Building Renewal (CHOBr) Project team review all punchlist items discovered during the one-year warranty inspection to determine how the quality control (QC) reviewers overlooked those items during prior inspections...