Cannon House Office Building Renewal Project’s Punch List and Warranty Work Process Lacked Sufficient Oversight
Report Information
Recommendations
Cannon House Office Building Renewal Project’s Punch List And Warranty Work Process Lacked Sufficient Oversight
We recommend that, for the remaining contract phases (Phases 3 and 4), the Cannon House Office Building Renewal Project team update its written quality control procedures to ensure compliance with all requirements for punchlist items prescribed in the...
We recommend the Cannon House Office Building Renewal Project team conduct a review of all punchlist items for Phase 2 to ensure it has properly identified each item and listed the correct status for each item (i.e., open or closed).
We recommend the Architect of the Capitol (AOC) consider tying the start of contractual warranty periods to Final Completion, rather than Substantial Completion, to ensure that the AOC does not lose warranty coverage on work completed after Substantial...
We recommend the Cannon House Office Building Renewal Project team ensure it maintains sufficient documentation for all punchlist items, to accurately identify (1) the work completed to closeout punchlist items and (2) the individual who approved the...