We recommend that the Architect of the Capitol revise and fully implement a process that ensures compliance with construction contracts, project specifications and any other requirements prescribed for substantial and final completion and document justification and approval for all deviations. This process should be applied to the awarding of substantial and final completion on all remaining Phases of the Cannon House Office Building Renewal Project.
Date Issued
Recommendation number
1
Status
Open
Significant Recommendation
No
Questioned Costs
$0
Funds for Better Use
$0